La Brasca: deterrent parking and express link in the works




                                                                                                        by Milena Radoman
          Nothing has been decided yet but, one day, it may be possible to park your vehicle in the La Brasca
          car park at the A500 exit and take public transport to Fontvieille...


          The hypothesis of a La Brasca-Monaco link   Waiting for a green light from France  fitting square pegs into round holes. There is
          is one of the projects has been talked about   France is said to have “shown interest” in the   no question that the ACM's Grand Prix needs
          for years; even before 2017, when Monaco   works, without yet giving the green light to   will not be met,” assured Céline Caron-Dagioni,
          acquired the 20-hectare piece of land, a   Monaco authorities. Ultimately, this La Brasca   who has consulted on this subject with the
          strategic logistics site for numerous events,   station could even be connected to Nice, via   President of the ACM, Michel Boeri.
          such as the Grand Prix and the Yacht Show.   an underground tunnel: “Some officials from
          The cost of the operation: €20 million to acquire   the Alpes-Maritimes are calling for this. Others   “Concrete cathedral”
          the surface and subsoil of this land.  do not have quite the same position. I say   If the park-and-ride and express link project
                                              'why not?' but it is in the longer-term future,”   is supported by the majority of the National
          2,400 passengers per hour and two or three   suggested the Minister of State, in front of   Council, the project nevertheless raises many
          minutes' travel time…               representatives of the National Council. “We   questions. “I am uncomfortable with the idea
          Located in the town of Eze at the exit of the   are cautious and ambitious. Since last year,   of creating a concrete cathedral to store cars
          A500 tunnel towards Monaco, this land could   we have launched a Four-Season study*, an   which will travel and pollute 90% of the way
          one day house a park-and-ride facility and an   essential prerequisite for any procedure in this   to Monaco and which will park there with a
          express link to the Principality - but by what   area and it is possible that we will consider   carbon impact which will not be, I think, very
          deadline? “These are priority objectives for   certain feasibility studies fairly quickly,”   favourable - even though there is already
          the Principality. Naturally, to achieve them   announced the Minister of State, Pierre Dartout,   an infrastructure, the train. This structure
          requires agreements with France, since these   soon due to meet the new French Minister for   exists, it is ecologically responsible and it is
          facilities are located, almost entirely, in that   Transport, Patrice Vergriete, who has replaced   already favoured by many workers,” expressed
          country,” indicates the Monaco government   Clément Beaune.              National Councillor, Roland Mouflard, during
          in its Mobility Plan. “Access to the area would                          the examination of the initial 2024 budget.
          be via a crossroads to be created on the   Alternative solution for the Grand Prix
          Moyenne Corniche. The programme of the   The objective of this project is, above all,   * Four-Season environmental studies began in September
          operation would include, in addition to at least   to streamline access from the west of the   2023 and will require 13 months' work.
          3,000 light vehicle parking spaces, places   Principality. Nearly 15,000 vehicles pass
          dedicated to the storage of heavy goods   through this area every day. “Traffic jams
          vehicles, tourist coaches, as well as areas   often form just before the Principality, at the   La Brasca-Monaco connection in
          reserved for events' logistics. Finally, the last   motorway exit. Some people can't take the   figures
          level would host the station of an express   train. These are often commuters coming from   • Length of the link: approximately two
                                                                                       kilometres
          link to the Principality, the arrival of which   the valleys, living outside the public transport   • Elevation gain: 200 metres
          would be at Fontvieille,” he specifies, without   network. We can resolve this with a car park   • Slope < 15% with slope variation
          revealing the mode of transport that could   and underground connection to reach the   • Journey time: between three and
          be chosen (underground funicular, metro or   Principality,” explains Céline Caron-Dagioni.  four minutes
          other). The only characteristics known are   In the event that the project comes to fruition,   • Type of material: not defined at this
          that it will be able to take 2,400 passengers   a replacement solution will have to be found   stage
          per hour from La Brasca to Fontvieille in two   for the Automobile Club of Monaco (ACM)   • Target capacity: 2,400 passengers
          or three minutes…                   which stores the Grand-Prix and Monte-Carlo   per hour
                                              Rally facilities at La Brasca: “We are used to