          Interview with Christian Estrosi:

          “A real regional RER train service” between Cannes and

          Menton                                                                                        By Milena Radoman




          A metro, a new PACA train line, a maritime shuttle, a new bypass: the Mayor of Nice and President
          of the Nice Côte d'Azur Metropolitan Region, Christian Estrosi, gives an update on the progress of
          these mobility solutions.


           METRO                              given the opposition of Mayor Xavier Beck?   if it is far from perfect, the situation has clearly
          At what stage is the planned 9.5-kilometre,   Do you think other projects could relieve   improved and it will be even better tomorrow,
          part-underground metro between the Nice   traffic congestion between Nice and Monaco?  since we will double the timetable by 2025
          area and Monaco? Have feasibility studies   The constant flow of vehicles on the RM 6007   with the opening to competition.
          been carried out on the French side? What   requires decisions to be made. More than   The new line should also help improve things.
          would its route be?                 30,000 vehicles use this road every day and   After years of withdrawal, where lines and
          Since 2008, we have planned a metropolitan-  the flow is likely to increase further. Current   stations were closed, the announcement of a
          wide transport plan for 2030, with a dual   infrastructure will not be enough.  new line is really good news. In total, we should
          objective: to reduce automobile traffic flows   We are all working together, with the Principality   be able to go from the 69 round trips per day
          and improve air quality. Travel between the   and associated institutional players, to put in   offered currently to 120 round trips per day
          Nice Côte d'Azur Metropolitan Region and   place solutions, just as we did recently with   in 2025, for a daily total of 70,000 travellers.
          Monaco is a subject of concern and we are   the creation of the new Beausoleil motorway   On the Cannes-Menton axis, the timetable will
          working on all avenues, including the idea of   interchange put into service by ESCOTA.  be identical during off-peak hours and peak
          a high-frequency railway line - why not in the   For our part, we are making progress on   hours with a train every quarter of an hour all
          form of a metro between Nice and Monaco   several developments in Cap d'Ail, including   day long: a real regional RER.
          with above-ground and underground sections?  the creation of a hopper on the Moyenne   For our part, we have already made good
          As this is a state-to-state issue, the feasibility   Corniche and studies with a view to widening   progress in making rail traffic more fluid and
          studies, the unveiling of the route and the   the hospital roundabout and continuing the   we are also making progress on infrastructure.
          impetus can only come from France and   boulevard du Jardin Exotique to absorb traffic   Since the inauguration of the station at Nice
          Monaco. As for me, I am obviously in favour   without breaking capacity. All these projects   Airport in September 2022, it is now possible
          of this project, as I had the opportunity to say   aim to respond to the increase in traffic, to   to move very quickly from plane to train and
          to the Minister of State, Pierre Dartout, and to   avoid traffic jams and slowdowns which are   to reach Monaco. We already count 6,500
          the former French Prime Minister, Elisabeth   very painful for users and seriously harm air   users per day compared to 2,900 at the old
          Borne; and as I have had the opportunity to   quality. During rush hours, when the de Gaulle   Nice Saint-Augustin station - more than twice
          repeat as often as I can. It would be a huge   intersection is congested, we often have to   as many!
          step forward.                       close the Rainier III Tunnel for safety reasons,   And that's just the beginning. We will go
                                              which further aggravates the problem.  even further with the future Saint-Augustin
          For the moment, Monaco seems to be                                       multimodal exchange hub which will eventually
          banking on the creation of a deterrent car   TRAIN                       host the Nice Côte d'Azur Airport, France's
          park in La Brasca, which could accommodate   For the Vice-President of the PACA Region,   second-busiest, as well as the new Nice Airport
          a station for an express train link to the   Jean-Pierre Serrus, the new PACA train line,   TER and TGV station, the first bioclimatic
          Principality. How is Nice positioned on this   which should see its partial commissioning   station in Europa! It will bring together three
          project? Have you done feasibility studies?   begin from 2026, is “the railway project of   tram lines, the largest bus station in the
          Could this be the first stage of a metro for   the century.” Do you share this opinion? What   department, served by urban and interurban
          Nice?                               are you expecting of it? On the other side of   buses, as well as bicycle facilities. It is not
          Such parking will, in any case, be useful to   the department, what is the status of your   the new line alone which is the railway project
          alleviate traffic flows in Monaco and in our   RER local train project which would connect   of the century, it is this entire set of projects
          metropolitan network, specially if it integrates   Nice to the Sophia Antipolis business park   which allows us to fully enter the 21st century
          a last-mile logistics platform. Obviously, this   via Villeneuve-Loubet and Antibes?  of the railway!
          project led by the Monégasque state has my   Since my election as Regional President at the
          full support.                       end of 2015, I have been keen to improve the   How will it fit in with the Genoa-Nice Airport
                                              TER offer so that it becomes a real alternative   line project? With Giovanni Toti, President
           ROADS                              to the car. We had inherited a network that did   of the Liguria Region, and Claudio Scajola,
          How is the project to create a bypass on the   not meet needs, with 20% of trains late and   Mayor of Imperia and President of the
          Moyenne Corniche in Cap d'Ail progressing,   10% of trains cancelled each day. Today, even   Province of Imperia, you would like to see