           Le projet Charles III vu depuis Fontvieille / The Charles III project seen from Fontvieille
          and posed structural problems that could   that a project will be finalised in June 2025.   filed a civil lawsuit in the criminal part of this
          have been anticipated. Further studies led to   No doubt it will be a hybrid of the three   case. We’re keeping an eye on this.
          project 1B, which was a bit monstrous; the   propositions.               J.A.: It’s a waste of this land.
          port would have had to be almost demolished   J.A.: The first time I saw this project, I
          and Boulevard Albert II would have had close   immediately pointed out that it would be a   You are going to meet with Christian Estrosi,
          in order to build it... At the end of 2023, we   miracle if we managed to do it; it was a fanciful   so will you raise the subject of the metro
          learned at the budget meeting that this project   project without thinking about the urban   again?
          had been abandoned, despite the fact that   functions of the neighbourhood. We started   T.B.: Before launching projects, we need to
          €38 million had been spent on the design   out with a fantasy idea without considering the   study their feasibility. Rather than talking about
          work... That's when we were presented with   inner-city logistics of an area where thousands   a metro, I prefer to talk about an additional
          the variants. Project 1C, a smaller version   of workers are present.    mode of transport between Nice, Monaco and
          of 1A and therefore of 1B, with the same                                 Ventimiglia. Let's wait and see what the new
          architectural style from Socri. This had the   The new CHPG Hospital: will it exceed 1.5   TER service will be like. But in any case, the
          advantage of using the structural studies   billion euros when in 2011, the cost of the   current options available are not sufficient to
          and, above all, of Socri financing the entire   project was estimated at 550 million euros?  reduce motorists. In absolute terms, the new
          project (4 years of building work), in return   T.B.: It will reach 2 billion euros and   mode of transport can take any form we want
          for long leases and the use of the retail   a construction duration beyond what is   as long as it meets the desired objective. This
          space. The second variant, which is less   reasonable,  with  completion  in  2035.   decision will probably be taken in Paris, not
          complicated because the structure does not   Which means that the hospital would be   at regional or local levels as the project could
          span the road (three years building work + 18   technologically obsolete… Now there’s a tower   also attract European funds.
          months of design work since we'd be starting   4, a Cape Canaveral which has enormous   J.A.: In the meantime, what matters is the
          from scratch), is less expensive and has the   financial consequences.   traffic density and roads that are sufficient
          advantage of keeping the shopping centre                                 to enable this density. It’s really a question
          open and renaturing it. The 3  option is a   Has the project for the Esplanade des   of political intent. It has been proven in all
                                 rd
          simple modernisation, with no urban flow   pêcheurs been completely abandoned?  cities. If you invest more in roads, you will
          between Fontvieille and La Condamine.  T.B.: An agreement with Antonio Caroli had   have more cars; if you invest more in public
          Didier Guillaume, Minister of State, wants   been reached. The project is blocked by an   transport, you will have more people not
          to review the venture and he has told us   appeal by Patrice Pastor. The Government has   using their cars.